Float is the amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date or violating a schedule constraint. Calculated using the critical path method technique and determining the difference between the early finish dates and late finish dates.