Pedro Franco and Wesley Glenn explain how T.D. Williamson uses operations science to tackle the complexities of high-mix, low-volume manufacturing and enhance overall efficiency.
Pedro Franco and Wesley Glenn discussed how T.D. Williamson has adopted operations science to address the unique challenges of high-mix, low-volume production. Franco described the company’s efforts to modernize global manufacturing processes, focusing on strategies that balance the inherent variability of their production environment with the need for efficiency. A central element of this approach is the use of “CONWIP loops” (Constant Work-in-Process), a system designed to control workflow and prevent bottlenecks.
Wesley Glenn expanded on these ideas by highlighting the technical tools and data-driven methods that support their production system. He detailed how factory physics models are used to pinpoint bottlenecks and guide resource allocation. These techniques have significantly reduced work-in-process inventory and cut lead times from seven weeks to just three weeks in some operations. Despite managing over 33,000 part numbers and navigating complex supply chains, the company has achieved measurable improvements in efficiency and responsiveness.
The presentation concluded by emphasizing the importance of building a culture that prioritizes continuous improvement and adaptability. Both speakers encouraged professionals to adopt operations science principles to address modern manufacturing challenges and prepare for future demands.
[00:00:00] H.J. James Choo, PhD: We’re going to continue on from the theme of the day. One of the things that many companies are trying to do is move work off site and leverage standard products. And one of the hope or the belief is that whenever we talk about applying operational science to construction, they say manufacturing is easy because all they do is mass manufacturing of standard products.
[00:00:31] H.J. James Choo, PhD: However, you’d be very surprised how many different variations of quote unquote products they’re actually making and what it takes to run a manufacturing operation. Because a lot of them are now faced with dealing with low volume, high mix. And the variability they see is a lot greater than construction, you’d be surprised.
[00:00:57] H.J. James Choo, PhD: And to actually take us through that, what it means to apply operation science in a dynamic, high mixed, low environment we have invited Pedro. from T. D. Williamson. Please come and join the stage. As I introduce you, Pedro is the senior director of global quality and operations excellence at T. D.
[00:01:21] H.J. James Choo, PhD: Williamson. He is responsible for building a stre strengthening product and services delivery system. And Wes is a process innovations manager at T. D. Williamson and prior to that he was an application analyst and mechanical engineer at the, at a company. Okay? Take it away.
[00:01:42] Pedro Franco: Thank you James.
[00:01:43] Pedro Franco: Appreciate the introduction and the warm welcome. I lead the TD Williamson Global Operational Excellence Team, and I’m also responsible for a charge and that is to transform our global manufacturing operations across the across the globe. And we’re gonna do that consistent with an operations base.
[00:02:06] Pedro Franco: science approach. Wes Glenn is our principal operations science practitioner, and he’s also our factory physics modeler. We’ve talked a lot about modeling. We also use the the model to help us in what we’re trying to achieve as well. He’s also our process design engineer. Wes and I will be co presenting application of operation science in a dynamic high mix, low volume environment.
[00:02:35] Pedro Franco: Okay. We have quite a bit of information that we want to convey and share with the with the group here. And so we want to really be mindful of the of the time so that we can cover everything, including a question and answer session there towards the end. We thought that to this end, a journey type storytelling approach would be instrumental.
[00:02:58] Pedro Franco: And so we’ve got a slide here that we’re going to be covering and we think that this this slide helps us provide the right amount of context for the journey that we’re, we’ve embarked upon trying to employ all of these operations based science approaches in this in this unique manufacturing environment that we’re in.
[00:03:21] Pedro Franco: So I’m going to briefly cover mile markers or the milestones one through four, and then I’m going to hand it over to to Wes who’s going to walk us through. In detail because we believe that’s the crux of what we want to try to convey today is the experience that we came across when we were traversing mile markers five through seven.
[00:03:42] Pedro Franco: Okay, there’s quite a bit of information that he’s going to share with that. And then what we’ll do is we’ll come back. You’ll turn it back over to me and I’ll briefly update where we stand on the rest of the on the rest of the journey. T. D. Williamson has been a family owned business for over 100 years.
[00:04:01] Pedro Franco: That’s saying a lot. If you stop and you think about it how many companies have been around for 50 years? That’s a heck of an accomplishment. And how many have gone away after 50 years? So 100 years is really a significant, accomplishment. The the business that we’re gonna be focused on that we’re gonna be talking about is T.
[00:04:22] Pedro Franco: D. Williamson’s hot tapping and plugging business. We provide goods and services to pipeline operators so that they can provide they can keep it in the pipe, keep production flowing, and it’s it’s vitally essential to any country’s national infrastructure. The HTMP business essentially produces five things.
[00:04:46] Pedro Franco: It’s five products that we put out when you Boil it down to its essence. And they are as follows. We manufacture tapping machines. Okay. We manufacturing, we manufacture isolation valves that are used along with those tapping machines, the isolation fittings that are required to do those interventions, housings, and adapters.
[00:05:05] Pedro Franco: That’s it. Five, at the highest level, five, five products is what we produce. They say that the one constant in life is is change. And in July 2022, the winds of change blew at T. D. Williamson because a private equity firm out of Houston decided that they were going to take a majority stake In T.D. Williamson.
[00:05:30] Pedro Franco: So after 100 years, T. D. Williamson is now majority owned by a private equity firm outside of out of out of Houston with the with the acquisition came a challenge for T. D. W. And that was to increase the throughput across the global manufacturing footprint. So that was the that was the challenge that was set.
[00:05:52] Pedro Franco: And to meet that throughput challenge was My recommendation was not single piece work because we knew that was not going to be the answer for our manufacturing environment. Previous attempts at trying to implement a lot of Toyota production system those standard offerings, mass producing them, they just were not going to work in our environment.
[00:06:23] Pedro Franco: So my recommendation to the leadership. And to the to the private equity firm was that we pursue an operation science based approach.
[00:06:40] Pedro Franco: All right what I’m going to do is here very quickly, I’m going to walk you through the first three mall markers here on the on the journey map. I’ve, indicated that back in July of 2022, the acquisition was was made, the edict was was given, the mandate, we’re going to increase throughput and that gave rise to us Working very closely with the factory physics folks.
[00:07:07] Pedro Franco: And what we ended up doing was convincing the organization that we can employ factory physics and the operation science based approach as a demonstration to prove out the concepts. We had our fittings, lineup. We were struggling at the time with lead times that were something on the order of about seven weeks.
[00:07:28] Pedro Franco: The market really required them to be three weeks. And so we took on the challenge. And probably inside of, I want to say less than four months, we went ahead, started working very closely with with Dr Chu and the team. And we started to model the the flow through the through the plant for, large diameter fittings.
[00:07:50] Pedro Franco: And what we found was a number of things. Number one is what we found was the working process that we had out on the shop floor at any given times was about four times. What it was required to to be. And that was driving up cycle times as the, as a result. The other thing that we found is we discovered that we had all kinds of inventory just sitting out in places that was also driving up that was driving up our, cycle times.
[00:08:15] Pedro Franco: So we went to work, we designed a constant work in process con whip. It’s a form of whip control. And we started to control how much work we would release out on the shop floor. We started to slowly drain. The inventory that we had in the system. And as we were doing that, we were monitoring it. And what we observed is that things were starting to flow long story short.
[00:08:36] Pedro Franco: At the end of about four months, we got to the point where we were on average producing something like less than one fitting per day. And at the end of those four months, we were producing something on the order of about four fittings per day. We got the lead times down to three weeks and our on time delivery performance to those three weeks lead time published lead times.
[00:08:58] Pedro Franco: Was on average two weeks. So it was a resounding success. We were then asked to expand the concept to another part of the portfolio, our DS equipment here. It’s a little bit more complicated because the DS equipment, excuse me, the DS equipment has on average, when you blow up the the bill of material, it’s got something like.
[00:09:17] Pedro Franco: Between 50 and 70 line items when you blow up the bill of material. So the complexity ended up, increasing as a result, but we took on the challenge. We follow the same, process. We modeled all of the part numbers through the through the C suite model. We identified where all of the work centers that were highly utilized.
[00:09:39] Pedro Franco: So we identified where the constraints were, and then we started working on designing constant working process or con whip and started putting in place the the whip control. And what we found is that as we started to do those things and we started to lower the working process, we got the we got the flow that we were looking for.
[00:09:58] Pedro Franco: And there again, more resounding success. However, what we discovered was that as we started to expand the product portfolio onto this new mode of operation, we started running into issues with the old mode of operation. So we had one foot in the new mode of operation where we’re controlling work in process for large diameter fittings.
[00:10:19] Pedro Franco: For the DS equipment, with good success, but because there is so much overlap in the plant. We’ve got 52 work centers, and the remainder of the product portfolio was being managed through a traditional push type system. So we started to see where there were conflicts that were starting to arrive. So we arrived at a decision point, and that’s mile marker number three?
[00:10:43] Pedro Franco: I believe, and that was, okay, a decision point around how do we end up getting the entire plant on CONWIP. The remaining the remaining excuse me, the remaining mile markers, four through seven Wes is going to walk into some of the de walk you through the details how we ended up doing.
[00:11:04] Pedro Franco: Something to keep in mind, I talked about earlier, there’s only five products that we essentially produce. But those five products in our, product catalog equates to 33, 000 finished goods part numbers. Think about that for a second. 33, 000 finished good part numbers that we’re responsible for manufacturing out of our plant.
[00:11:27] Pedro Franco: And what we discovered is, okay, while you think that’s daunting, When you blow up the bill of material on those finished goods part numbers, and on average, those 33, 000 part numbers is about 50 line items on an exploded bill of material. So we’re talking about really part numbers that exceed a million.
[00:11:49] Pedro Franco: And the reality of the matter is with that level of complexity, how were we going to get the entire plant on whip control and how are we going to get to a new mode of operation? Where we can enjoy the benefits of all of the things that we discovered and we experienced with the first two demonstrations that we had done.
[00:12:07] Pedro Franco: So with that being said, I’m going to go ahead and turn it over to Wes. Wes is going to walk us through some of the details on how we got there.
[00:12:19] Wesley Glenn: Alright I’m going to rehash a few of those details as I tell the story. So Pedro talked about our product portfolio and I like to put a face with the name. I’ve condensed it down further into three categories. You can see the little triangle and the little box in red. And that’s what a fitting is.
[00:12:39] Wesley Glenn: Those are welded onto our customer’s pipelines. Then in the middle, the orange box is the valves, adapters, and housings section that Pedro talked about. And then at the top in the green box, we have machines and we have two varieties of machines tapping machines and plugging machines. So on the fittings, there are relatively our simplest product that we make.
[00:13:03] Wesley Glenn: They have two sub assemblies. And then they’re combined in one for a total of 15 to 20 components. And the middle portion, those are slightly more complicated, somewhere between 10 and 50 components, typically two, again, two sub assemblies that are then welded together. And then our machines are where we get the crux of our variability and all of our sub assemblies.
[00:13:29] Wesley Glenn: They can range from four sub assemblies all the way up to 10 or 12 as they grow in size. For all of these components, we range from 2 inch to 36 inch in size. I’m only telling you that so you understand that whenever Pedro talks about the 33, 000 finished good part numbers that we have, it’s because we offer them in such a large size large size envelope.
[00:13:55] Wesley Glenn: And in different types of markets high pressure flow, low pressure flow and so I’m laying this groundwork so you understand just how much variability we’re dealing with. For those of you who have ran the SPS model, we don’t even get a map out of our model. We have over 100, 000 process steps in our models typically.
[00:14:17] Wesley Glenn: So the plant that Pedro and I support, the plant that Pedro and I support is responsible for delivering these products to our customers and our services department. And that plant has about 55 or 52 work centers. We have five cellular manufacturing centers. And we have five assembly cells. And I’m just laying the groundwork so that you understand further in the presentation, why I’m telling you these things.
[00:14:46] Wesley Glenn: And so you can see some of that. So with all of those different routes, that large diameter fitting demonstration that we did with factory physics is the closest thing we have to a dedicated line. If you look at all of our other routes, it’s basically spaghetti across the entire plant. There is no streamlined approach.
[00:15:06] Wesley Glenn: Everything goes everywhere. So as soon as we started to model the whole plant, because we needed to get the whole plant on WIP control using ConWIP, we ran into a problem because we have 33, 000 finished good part numbers. So we were trying to wrap our head around how do we do this? And so we did an analysis called Runners, Repeaters, and Strangers.
[00:15:29] Wesley Glenn: And so we looked over the last six years, and we said, what do we sell every week? What do we sell every month? What do we sell every quarter? what do we Or what do we sell every year? And that’s what you see here. In the green, we have our runners. Those are things we sell weekly. It only came out to 500 part numbers.
[00:15:48] Wesley Glenn: And then we have our repeaters. Those are things we sell quarterly. That came up to another 700. And then what is our strangers. And we make a lot of strangers. 5, 000. We didn’t want to run this through the model. Our models already take a long time to generate. So we looked at the revenue impact at the stranger level.
[00:16:12] Wesley Glenn: Keep pressing the wrong button. So again, this is a little bubble chart of the same thing. You can see the big red. That is our strangers. That’s the largest portion of part numbers that we observe, but our revenue clearly comes from our runners. That’s what our customers need day in and day out.
[00:16:30] Wesley Glenn: So this was unfeasible for us to try to wrap our minds around. So then we looked again at the strangers and we did a Pareto and we found that the 80%. That 10 percent of the part numbers make up 80 percent of the revenue we get from the strangers. And so we were able to rationalize this a little bit better by just taking that, that, and that encapsulated 95 percent of our revenue across all of our part numbers.
[00:16:55] Wesley Glenn: And so we used this result, which whittles us down to 1800 part numbers. And this is where I get that number for a hundred thousand process steps. I actually had to call Chet and say, Hey, my model’s not running. What’s going on? And it’s basically, Oh, you have too many process steps. We have to increase how many lines we have available.
[00:17:16] Wesley Glenn: So we ran this model and we found that for our plant, we had nine bottlenecks and we still haven’t got, it’s still not easy to do yet. We’re still, we still haven’t found a solution. We’ve just found where the problems are. So how are we going to, how are we going to create con web loops or implement whip control in our factory or around these nine bottlenecks?
[00:17:36] Wesley Glenn: I mentioned it was spaghetti and that’s spaghetti goes everywhere. And so across these nine bottlenecks, we can have the same routing that goes across all nine. And that’s a frequent, and that’s frequent. Those machines that do a lot, they do a lot. So we had to figure out how are we going to do this? So we got together our production team, our planning team, and some of our other plant managers, and we were telling them we, we can do the model based on by different types, by different sizes.
[00:18:05] Wesley Glenn: But every time we try to put a flow together, there’s so much overlap, we were having a hard time. And one of our colleagues came up with an idea. And he called it the black box. We’ve since renamed it to a bottleneck hierarchy, because that’s more descriptive of what it actually is. And so the concept here is you have nine bottlenecks.
[00:18:29] Wesley Glenn: Let’s make the loops around the bottlenecks. And so basically how this, works is all these routings are going everywhere, but we have different bottleneck rates for each machine. And so we said, okay, which bottleneck has the slowest rate? Okay, we’re going to make that one the king. And so for all the routers that go through multiple bottlenecks, we’re going to not even consider it in these other product flows.
[00:18:54] Wesley Glenn: We’re going to, this one bottleneck is going to absorb all of them. And that’s how we started to rationalize that. So we had rank one, rank two, rank three, and we had eighteen hundred parts finished good parts, and so all their different routings, we were able to push them into these different loops according to this bottle, bottleneck hierarchy.
[00:19:16] Wesley Glenn: Okay. And that’s how we were able to create our con whip loops, our constant work in progress loops. And this was this approach works very well. Everyone started to understand this because, we have routes that go across so many different, places by doing this we knew that we’re going to have, we were able to control the whip in a different way.
[00:19:44] Wesley Glenn: So back up. So we implemented this in April of this year and it was going remarkably well. In fact, in the second week on Monday, the second week of April. Our plant manager came to us and he said, I don’t really know what’s going on. We’ve shipped twice as much revenue than this in the first week than we normally do in any month.
[00:20:09] Wesley Glenn: And so obviously we’re very ecstatic about that, but he doesn’t know why it’s going right. We should have recognized the red flag. We were really pleased with the results, but around the third week of April there was some tailwinds from the old mode of operation and the need for a certain amount of visibility.
[00:20:33] Wesley Glenn: That we hadn’t necessarily gotten to with the new mode of operation. And because of that, some of the the forces collided. And unfortunately, we reverted to the old mode of operation. And when we did that, we we had to go into diagnostics mode and figured out what’s going on. That what did we miss?
[00:20:54] Wesley Glenn: Why did this happen? And so we identified a vicious cycle. We spent the next four months examining the system and the current state and where we’re at. Saying, okay, so what went wrong? So we start with this. We, have lots of expediting and what we found too, was that if you’re familiar with MRP, we’re firming almost every order that comes in.
[00:21:22] Wesley Glenn: So we’re saying we can do this project and we’re saying that we can make these parts and we’ll put them into our system and we’ll lock our schedule almost six to eight months out, which is un, unreasonable in a manufacturing environment, especially in a low volume, high mix environment. Yes. Low volume high mix.
[00:21:43] Wesley Glenn: And what we also saw was because of that, we were releasing things far too soon. So our WIP was completely out of control. And so because of that, what happens is we end up getting excessive rescheduling. And when I say excessive rescheduling, I’m not talking about one or two reschedules here or there.
[00:22:01] Wesley Glenn: I’m talking about an order of magnitude of 150 reschedules per day. Of moving orders around. And when you do that, what you get up getting is you get excess and uncontrolled and stagnant wit,
[00:22:18] Wesley Glenn: which leads to the reduced ability to have capacity. You can’t release anything else. You can’t flow easily. Where are you going to put it? Everything’s already on the floor. And this increases your cycle time because now the question doesn’t become, the question becomes, what am I going to work on today?
[00:22:36] Wesley Glenn: I have 50 things. Which one’s the most important? They’ve all been rescheduled at least once. I don’t know what that does is it just increases your lead time. And when, and you know what that means? If your lead time increases we can probably beat that by releasing it earlier.
[00:22:59] Wesley Glenn: So after a while you get fed up. And so what that ends up doing after a time delay, your customers stop stop ordering from you. They cancel their orders, which leads to more uncontrolled stagnant excess whip.
[00:23:19] Wesley Glenn: Let’s see. Yeah. So this is another little subsection that. As you increase the amount of whip that you have on the floor and you keep changing people’s priorities, you run into quality issues, which degrades your ability to flow through the shop. And in the longterm, what happens is everyone, your customer, your planners, and your sales folks, they start to lose faith in your ability to deliver, which then leads us back to more expediting.
[00:23:50] Wesley Glenn: So the, place we’re at in our journey now is we’ve, tasted the good wine. We, want this, we see that it can work. And so now, we’re tasked with how do we break this vicious cycle? And that’s where we’re heading next. We’re, starting to break this vicious cycle. I’ll turn it back over to Pedro.
[00:24:09] Pedro Franco: Thanks Wes. Yeah, so where we are at the journey now is we’ve shared. This vicious cycle as part of the diagnostic work that we did with all of the key stakeholders. And they all agree, right? When we walked them through it, does this make sense? Does this make sense? Yeah, I lived that every single day.
[00:24:27] Pedro Franco: So they all agree that this is what’s going on. However, despite everyone understanding that this is what’s going on, it’s the devil that they know, right? And so we’re up against some of that. This is what people are comfortable with living with this. And so now part of the journey for us is, okay, how do we get them comfortable being able to move back to getting the whip control, getting those Getting those conduit loops re implemented and what we found was that there’s a change management component to this and we’ve had to adopt a little bit of a change management strategy.
[00:25:05] Pedro Franco: And so what we ended up doing was we negotiated with the production planning group and we said, Hey, look, you know when it’s time to go re implement this and we negotiated a date to turn it back on. It’s going to be January 6th, so it’s just a few weeks away. What we agreed that we would do is that we would.
[00:25:23] Pedro Franco: Not introduced the fistful first and system first out when we introduced it back in April, we had turned on the fistful the first and system first out and automatically what that did was it took all of the orders that that were old, right? The oldie moldies all of a sudden came up to the top of the list and said, Hey I need attention.
[00:25:43] Pedro Franco: And and then that started competing with other interests. And what we did is we, said, look, we’ll give you the ability to be able to. Move a certain amount of things, but beyond a certain point, once it’s released out onto the shop floor you can’t move, you can’t move things.
[00:26:01] Pedro Franco: You gotta follow, you gotta follow the discipline. So we’ve given them the opportunity inside of our virtual cues before we release it into the system. They can move things around to their heart’s delight. And so that seems to be received. And so part of the story stay tuned, But the plan is January 6th and we’re going to go ahead and turn it back on. And and move back in, in that direction and and hopefully by this time next year we’ll, be able to share with you where we are on the journey. I think we’ve got we’re over a few minutes, but James, not sure if we wanted to tackle any, Q and A’s or if we’re up against a hard stop.
[00:26:45] Audience Member: The stranger that you talk about that are basically custom made. There are not commodity items. I know for a fact because I’m in the oil and gas. So we work with some of your custom made product for those kind of product. Have you? You were talking about your stakeholder. Have you involved your customers in managing these?
[00:27:15] Audience Member: What are the type of conversation you’re having with your customers?
[00:27:20] Pedro Franco: So if I understood your question correctly, to what degree do we engage with the customers and have the discussion around the engineered to order type of.
[00:27:30] Audience Member: I’m on the side of expediting.
[00:27:32] Pedro Franco: Yes.
[00:27:33] Audience Member: I’m the one expediting you. So what is the conversation you’re having?
[00:27:40] Audience Member: Cause I want my product and I, want to know that in the queue, you’re going to do it and I’m, you’re going to favor me versus I work for BP versus Shell or Chevron or I’m going to be in your office every day calling you.
[00:27:54] Pedro Franco: So yeah, that’s an excellent, that’s an excellent question.
[00:27:57] Pedro Franco: Part of the part of the strategy there. A couple of things, number one is to the extent that we can start standardizing a lot of the engineer to order fittings is going to go a long way because then in that particular case, we can introduce something called a late product differentiation.
[00:28:12] Pedro Franco: So we could put things in semi finished good conditions, strategic inventory points so that we can compress the the lead time. And that way, when the order comes in for the specific. For the specific requirements, we can pull it out of a semi finished goods condition and then take it all the way through the balance of the process and get it to the finished goods.
[00:28:32] Pedro Franco: So that’s one of the strategies. The other thing is to the extent that we can continue to work on building up our strategy, our safety stock throughout the plant is going to put us in a position where we can free up a lot of those work centers. So what we’re trying to do really is, trying to move Move.
[00:28:51] Pedro Franco: towards selling the preponderance of the portfolio as much as we possibly can either out of a straight out finished goods configuration or a semi finished good configuration. I hope that answers your question.
[00:29:07] Audience Member: Yeah, for multiple reasons, none of us wants inventory. No, I don’t you don’t want to keep my inventory. I don’t want to keep the inventory. So it’s all these on time delivery.
[00:29:28] Pedro Franco: Anything you want to add?
[00:29:29] Audience Member: But, yeah, but I’m trying to see how I can talk to manufacturers like you in terms of production system.
[00:29:38] Audience Member: And say when when and how to say, okay, I’m ready. You’re ready. But I think you answer my question. Is the semi finished product? That’s where you we need to operator or customer and manufacturer. We need to agree on.
[00:29:59] Pedro Franco: Yeah, because there is always going to be some engineer to order. We can’t get around that.
[00:30:04] Pedro Franco: But the key is is to to have those those precious resources available to be able to handle those. And so to the extent that we can move to semi finished or finished good product, that that, that’s a big part of the strategy.
[00:30:17] Wesley Glenn: And if I can add something too, once we get the system up and operable as well, we’ll be able to give you much more reliable dates.
[00:30:27] Todd R. Zabelle: Can I add something to that? I think you guys have a huge opportunity. I would invite Sarah from BP down to your facility. Yes, absolutely. Absolutely. Archer in front of the Vice President of Sales. Let her say, we want to look at this from a value stream perspective. I’m from BP. I could maintain your whole business for you, Mr. PE guy,
[00:30:46] Todd R. Zabelle: But we would like to work together. It’s extremely powerful. We’ve seen many customers through the last couple of decades have the customer come in with that request. It’s amazing how fast the executives flange up when one of the big customers show up or even better if they don’t have all that customers business.
[00:31:05] Pedro Franco: Excellent point. We’ll connect. We will definitely connect. Anytime.
[00:31:10] Todd R. Zabelle: You might be the top seller guy once you leave.
[00:31:21] Audience Member (2): So I think you reflect a little bit about a lesson learned. Four months of forensics sounds scary to me. I don’t know how long you spent modeling the system and deploying. But what would you do differently? If you had to deploy this all over again and not have to do the forensics? Yeah. Did you involve operations in this modeling?
[00:31:41] Audience Member (2): I’m just really curious, what would you do differently so you would have a, one, one approach?
[00:31:48] Wesley Glenn: We had a few unique things that happened during the journey. We had done, I think, a very good job at doing change management, but about a month before we were launched, we had some turnover. I think that was a hamper.
[00:32:01] Wesley Glenn: That, that was something that was difficult. I think if that, that was one roadblock that we couldn’t perceive was gonna happen But I think earlier you guys were talking about biting off little pieces. And I think what I would have done differently is maybe bought a, suggested we bite off a little smaller piece to go to go first.
[00:32:23] Wesley Glenn: I think it was difficult to see, for me, from a systems perspective, you’re in one system and we need to be in another system, and I couldn’t see the bridge between the two systems. So I think what we did was we tried to jump into a new, system rather than find that in between. That’s, probably what we would have done differently.
[00:32:41] Pedro Franco: Yeah I, would add to that that the vicious cycle that we mapped out, we probably could have gone on a on a, discovery before we implemented it and mapped out that that vicious cycle beforehand because what we discovered was that we were affecting what we thought was a change.
[00:33:02] Pedro Franco: In a part of the system that was going to be sufficient to affect what we were looking for and what we understood afterwards was that it was affecting a much larger system and that was lost on us until after we mapped out the vicious cycle, that’s when we learned, Hey, wait a minute, we’ve got people inside of the organization who’ve got a vested interest in doing internal expediting, moving things around to jockey up to the front of the line.
[00:33:27] Pedro Franco: And so all of the disruptions that came along with that. We were not the, what we were not the wiser until afterwards. Yeah.
[00:33:34] H.J. James Choo, PhD: So one of the other things that I think we can convey, and this comes from just exterior, the discussions that we actually had, and as he actually just pointed out, they were shipping products at an un, unseen levels in the last 18 months.
[00:33:50] H.J. James Choo, PhD: That I think is a indication of performance from a product perspective, but it didn’t meet. The individual salesperson need to be able to expedite date, their products through the system and he actually talked about a case where the publisher lead time might be three weeks. And we if we stick to the web, it comes out in three weeks.
[00:34:08] H.J. James Choo, PhD: But sitting next to him, someone will be taking an order and someone will be calling, Can you give me in a week? And they will say yes, I’ll get it to you in a week and try to force their stuff to actually through the system, which would increase the web and so forth. So having to address that is what actually is taking them to Deal with not the technical aspect of the situation.
[00:34:29] Pedro Franco: Good point. Absolutely.
[00:34:32] Audience Member: I don’t need a mic, but let’s pretend that I do need the mic. So I think that is a win situation between what you guys are trying to do and your your customers. I think is I think is to explain to your sales people how to sell better your production system.
[00:34:58] Audience Member: And and and explain to I’ve been in situation where yourself, guys promise. And then it’s, a very difficult conversation escalate very quickly to the vice president of both companies being in a call, but it’s, yeah, it’s to, for me, this recommendation is to do a better job, but to explain your production system so that the customer can say my production system works this way, your production, where can we find the the the touching point, the win situation, yeah.
[00:35:44] Pedro Franco: If I understand you correctly the reason why you expedite today is because you’re, working under the fundamental understanding is that’s the way this production system works. I get my stuff when I expedite, right?
[00:35:59] Audience Member: The fact that I have to pay expedite the day one from the get go is because I know that I have to expedite your company or other companies. So I’m spending a lot of money because I know I’m not going to get it even from the front stand line that you are going to give me. And I’m also going to give you a deadline. I’m, you don’t know my deadline, but I give you a deadline. It’s probably two weeks. Two, three months before I actually need it because I know you have to take one.
[00:36:30] Audience Member: If there is a, if there is a better job at explaining your production system.
[00:36:33] Gary Fischer, PE: So it’s really clear the vicious cycle is bigger than that.
[00:36:39] Audience Member: The vicious cycle is bigger than that, yes.
[00:36:40] H.J. James Choo, PhD: And hence the invitation to visit I guess.
[00:36:48] Pedro Franco: I look forward to connecting with you and keeping the, discussion going.
[00:36:53] Gary Fischer, PE: That was excellent. Thank you very much for sharing your experiences with us. We look forward to having you come back.
[00:37:00] Pedro Franco: Appreciate it. All right.
PPI works to increase the value Engineering and Construction provides to the economy and society. PPI researches and disseminates knowledge related to the application of Project Production Management (PPM) and technology for the optimization of complex and critical energy, industrial and civil infrastructure projects.
The Project Production Institute (PPI) exists to enhance the value Engineering and Construction provides to the economy and society. We are working to:
1) Make PPM the dominant paradigm for the delivery of capital projects,
2) Have project professionals use PPM principles, methods and tools in their everyday work,
3) Create a thriving market for PPM services and tools,
4) Fund and advance global PPM research, development and education (higher and trade), and
5) Ensure PPM is acknowledged, required and specified as a standard by government and regulatory agencies.
To that end, the Institute partners with leading universities to conduct research and educate students and professionals, produces an annual Journal to disseminate knowledge, and hosts events and webinars around the world to discuss pertinent and timely topics related to PPM. In order to advance PPM through access and insight, the Institute’s Industry Council consists of experts and leaders from companies such as Chevron, Google, Microsoft and Merck.
Join us in eliminating chronic poor project delivery performance. Become a member today.